Page 1 of 1

Estimated time (min):0

PostPosted: Wed Oct 15, 2008 2:21 am
by aksinghv
Hi,

when i run Reports for Test Plan. I see
Estimated time (min):0


Where does it compute this value for estimated time? Is it implemented?
Where can we put this value, so that estimated values can be arrived.

Where do we enter actual time consumed for the test cases? So that comparison can be made?


Thanks,
Anjani Singh

PostPosted: Wed Oct 15, 2008 9:18 am
by fman
go to mantis an look for issue regarding this feature and how to enable/disable or use it.

PostPosted: Wed Oct 15, 2008 9:50 am
by aksinghv
Hi,

I went to the mantis. I could find:
http://www.testlink.org/mantis/view.php?id=1250

Currently, it can be done by custom fields. Let me see how i can implement this.


Thanks,
Anjani Singh

Solution implemented in 1.8RC1

PostPosted: Wed Nov 19, 2008 5:06 pm
by amkhullar

In the Testlink 1.8 RC2

PostPosted: Sun Dec 28, 2008 12:24 pm
by Ilissan
Hi,
Actually now i can see the Estimated execution time in the Test plan results,
but it shows only values per test case is it possible to see the summary of all test cases or its not yet implemented? and if will be?
Thanks!