management build

LATEST Official version.
Questions and discussions - NO ISSUES
FOR ISSUES => http://mantis.testlink.org

Moderators: Amaradana, TurboPT, TL Developers

Post Reply
integ
TestLink user
Posts: 2
Joined: Wed Sep 01, 2010 8:20 am

management build

Post by integ »

Hi,
have not I understood as I do to insert the test case for a build 2?
you could help me?

Would you be able the footsteps to follow?


I use the version 1.9 beta5s thanks
-----------------------------------------
Test Plan 1
Build 1
Test Case A Test case suite
Test Case B
Test Case C

Build 2
Test Case D
Test Case E Test case suite
Test Case F
Test Case G
---------------------------------------------

Test Plan 2
Build 1
Test Case A Test case suite
Test Case B
Test Case C


Build 2
Test Case A Test case suite
Test Case B
Test Case D
------------------------------------------------
fman
Member of TestLink Community
Posts: 3123
Joined: Tue Nov 15, 2005 7:19 am

Re: management build

Post by fman »

test cases are linked to TEST PLAN + PLATFORMS not to BUILD

test case linked to a TEST PLAN + PLATFORM can be ASSIGNED to TESTER, on BUILD BASIS
integ
TestLink user
Posts: 2
Joined: Wed Sep 01, 2010 8:20 am

Re: management build

Post by integ »

fman wrote:test cases are linked to TEST PLAN + PLATFORMS not to BUILD

test case linked to a TEST PLAN + PLATFORM can be ASSIGNED to TESTER, on BUILD BASIS


thanks for the answer.
..but I have not understood

In the same test plan I can have more builds?
or must I associate a build to a test plan and then a build2 with a testplan2?

can I create this situation?

Test Plan 2
Build 1
Test Case A Test case suite
Test Case B
Test Case C


Build 2
Test Case A Test case suite
Test Case B
Test Case D
Post Reply