Test Plan Report mixed Test cases

Posted: Mon Jan 17, 2011 10:53 am
by edv_harry
Hello,

i have open a ticket in the mantis tracker system for a long time.

the number is 0003758 and i wait for an answer.

Is there a problem in testlink 1.9 rc1 or is there a problem in my question ?


I need the function with differend plattfoms in the testplan.



Who can help me ?


Thanks

Sven

Re: Test Plan Report mixed Test cases

Posted: Tue Jan 18, 2011 6:53 am
by fman
you have to upgrade to stable release.

Re: Test Plan Report mixed Test cases

Posted: Tue Jan 18, 2011 7:44 am
by edv_harry
Hello,

yes.

At the moment i have again download the newest version of testlink.

But it is the same problem.

I have 2 plattforms(desktop, laptop) and 4 different test cases(a,b, x, y).

Then i create a new testplan and a build with the 2 plattforms.
Then allocate the cases a and b to the desktop plattform and the x and y case to the laptop plattform.
Then run the test with the result OK and have a look to the report.

In the report i see on the desktop, 2 case OK (a,b) and 2 case(x, y) not run

On the laptop plattform a and b not run but x and y are OK

Can you follow me and simulate the problem ?

best regard

Sven

Re: Test Plan Report mixed Test cases

Posted: Tue Jan 18, 2011 6:42 pm
by fman
think this issue will be part of 1.9.1 release. Please do some search on mantis for issues similar to 3758