Requirements Specification Report show multiple revisions?

Posted: Fri Jun 17, 2011 6:37 pm
by nathandelane
Hi I'm not sure yet whether this is a defect, but I have searched diligently across Google, these forums, and the user manual for an answer and so far I have come up with nothing. So I am simply asking first before I log a defect whether this is by design. I have a test project that contains a requirements specification linked to several tests, and the requirements specification is in version 1, revision 2. When I run the Requirements Specification Report, I get two instances of my requirement listed on the report. Is this by design? What does "freezing" the version do and will it affect my report? Is there any way for me to deactivate the old revisions? Any ideas on this? I am stumped. Aside from looking into the code, I am not sure what to do.

Thanks.

Nathandelane