Hello,

i'm looking for create a new Project from existing Test Plan but i want to keep the results of failed TestCases in the existing Test Plan for the new project too

Thanks a lot for your help

Re: How to Create Project and keeping Resluts?

Posted: Wed Mar 26, 2014 11:09 pm
by fman
1. not possible without custom development
2. it will be interesting understand which is the use case for this feature

Re: How to Create Project and keeping Resluts?

Posted: Thu Mar 27, 2014 7:53 am
by atab
fman wrote:1. not possible without custom development
2. it will be interesting understand which is the use case for this feature


Thanks fman,

the use case for this feature is that our customer required from 4 campaigns recipe containing the same test case and each campaign has resumed in the case of failure the previous year with results

Re: How to Create Project and keeping Resluts?

Posted: Thu Mar 27, 2014 7:55 am
by atab
I want to find a solution automatically instead of manually perform