Managing Actual and Remaining Execution Time

1.8 related questions and discussions.
Please upgrade to LATEST 1.9.x.
No more fixes for 1.8.

Moderators: Amaradana, TurboPT, TL Developers

Locked
maorazon
TestLink user
Posts: 10
Joined: Fri Jul 10, 2009 9:05 am

Managing Actual and Remaining Execution Time

Post by maorazon »

Hi,

Is there a way to identify how much time remaining to execute test cases?

What I did was create a custom field, estimated execution time in Test Cases.

I would like to know if I could use this information and add them up to come up with a timeline of how long these test cases would be run by adding the estimated execution time?

any ideas?
patel
TestLink user
Posts: 1
Joined: Tue Sep 15, 2009 8:52 pm

Add Custom Field to General Test Plan Metrics in Results tab

Post by patel »

Hello,
I am currently at the same stage as above:

I created a custom field, estimated execution time and am working on trying to use this information to find the remaining time left (sum the estimated execution time for the not run Testcases)and show this field in the General Test Plan Metrics in the Results section on TestLink.

I would appreciate if any of you could share your insights. Thank you.